Project start date 4th November  2016 Project end date 30th November 2016 Research to be started- 10th November 2016 Questionnaire for interaction with people and that for the survey of disease affecting people will be prepared by the team under the guidance of the teacher- to be started by the first week of a November2016 Talk- time with the Forest officer- After the survey is completed. ( to help interpret the survey report better) | 
3.4Special
Activities Plan:
                List
any special activities (e.g. Field trips or guest speakers) including dates.
| 
Visit from a Forest officer – | 
3.5Resource
Plan:
List resource that will be required
during the project and any other date constraints associated with them.
| 
Junior Science lab and the computer  lab: 1 science period per week for the
  duration of the project. Library Resources 
Online, books | 
3.6 Direct
Instruction:
List any planned direct instruction
sessions and link them to specific tasks if appropriate.
| 
Lesson: Forest our life line. 
Importance of forest 
Creating  a Survey 
Ppt and skit 
Chart presentation 
Collage work | 
3.7 Reviews
and checkpoints:
                Describe
how you will incorporate review meetings and checkpoints in the project
| 
 30 minute class meeting every week to discuss the progress
  of the tasks taken up and problems encountered by them during the same. A check point meeting for each 10-minutes meeting with each group separately twice a week | 