Work plan-Lesson 4

Work plan-Lesson 4

Sl.
No
TASK
SUB TASK
ROLE
START DATE
END DATE
PRODUCT
01
Launch project


04.11.16

30.11.16

Project launched
02
Deliver classroom instruction
Areas to be covered.
1.Define the project
2.Culminating products

Teacher
04.11.16

04.11.16

Initial classroom instruction is completed
03
Group selection
Students’ list

Teacher
05.11.16

05.11.16

Group selection is completed
04
Conduct research
Collection of Content on -
1. Environmental resources available to us.
2. The problems due to exploitation of the environment.
3. Significance of creating awareness about the problems caused by unthinking exploitation of the natural resources.
Student
05.11.16

22.11.16

Students recorded in the computer
05
Perform survey
Create survey/ interview questions , conduct survey/ interview, prepare survey/ interview report- Eliciting from group members and analysing.
Each member
08.11.16

18.11.16

Collected report
06
Programme sheet activity
Prepared based on curricular units and problem areas  in daily life affecting health
Student and teacher
18.11.16
19.11.16
Prepared
07
Advice meeting
Team prepare briefs
All team members
21.11.16
21.11.16
A meeting was held
08
Project presentation
Posting in the computer/blog
All

25.11.16

26.11.16
Completed
09
Assessment and grading
Prepare rubrics and assessment
Teacher
25.11.16
27.11.16
Completed
10
Refection and evaluation
Student reflection and evaluation, Teacher refection and evaluation
Students and teacher
28.11.16

29.11.16

Completed.
11
Project closed
Submitting the project report
Teacher
30.11.16


Closed

The project was completed as per schedule and the reports thereof prepared by the groups were submitted to the Principal. The project reports, like the project presentation, survey/ interview report, and the charts used for presentation were evaluated.